Development & Construction Update
The following is an overview of activities taking place at Island Palm Communities. If you have additional questions, please contact your community manager.
North Region
Helemano, Schofield Barracks, Wheeler AAF
New Homes (2,113)
Kalakaua • 637 (JNCO, SNCO, FGO, E09 and O06) 100% complete
Porter (includes Moyer area) • 753 (JNCO, SNCO, CGO) 100% complete
Kaena (part of Santa Fe Community) • 482 (JNCO) 100% complete
Wheeler (Wili Wili area) • 241 (JNCO/SNCO/CGO/FGO) 100% complete
Renovations (ongoing)
Canby, Wheeler and Helemano Communities (started July 2007)
Some homes in Patriot/Hamilton, Santa Fe, and Solomon
In Progress
Wheeler Community Center/Office
» Anticipated opening of office, activities room, fitness center and theatre is the second
week of March
» An opening date has not yet been determined for the swimming pool, spray park, tot lot
Future Development*
Phase I Santa Fe
» Turn over to construction for demolition July 2013, construction through 2015
South Range
» Development to begin October 2012, first homes to be delivered October 2013
Helemano
» Construction of homes in green field areas to begin 2012, first homes to be delivered
Summer 2013
*Dates subject to change